Gulf Breeze Stormwater Management Project


Project Overview

Implementing Organization
City of Gulf Breeze

DWH Project Funding

0

Known Leveraged Funding

0

Funding Organization

Florida Department of Environmental Protection

Funding Program

MOEX Clean Water Act Penalties (CWA)

Project Location: Florida1

Funding Source: MOEX
Controlling Document: Consent Decree Between The United States and MOEX Offshore 2007 LLC
Year Awarded: 2012

Project Details

Project Category

Project Actions

Engineering and/or Construction
Resilience
Engineering and/or Construction Resilience Water Quality Restoration and Maintenance

Targeted Resources

Built Environment
Infrastructure

Project Description

This project will provide more than $1.8 million in stormwater management infrastructure to the city. Urban stormwater runoff and nonpoint source pollution present the most significant continuing source of water and sediment quality degradation in the affected areas of the Panhandle, whose coastal waters received oiling after the Deepwater Horizon spill.Stormwater retrofits projects play a key role in protecting waterways by protecting water quality and managing flows.

Project Contact

Project Partners

None

Affiliated Institutions

None


Project ID: 298
Project Name: Gulf Breeze Stormwater Management Project
SourceUID: 6, 7
Latitude: 30.36442164
Longitude: -87.17317281
Country: United States of America
State or Province: Florida
County: Santa Rosa
Project Category: Environmental
Project Action: Engineering and/or Construction
Additional Project Action(s): Resilience
Additional Project Action(s): Engineering and/or Construction Resilience Water Quality Restoration and Maintenance
Targeted Resource(s): Built Environment
Targeted Resource(s): Infrastructure
Targeted Resource(s):
Anticipated Project Completion Year: 2015
Implementing Organization: City of Gulf Breeze
Implementing Organization Type: Local
Point of Contact – Name: Thomas Lambert
Point of Contact – Phone: tlambert@gulfbreezefl.gov
Point of Contact – Email: None
Other Partners: None
Affiliated Institutions: None
Link: http://content.govdelivery.com/accounts/FLDEP/bulletins/60f24d
Project Comments: This project consists of two work sites in Gulf Breeze. The cost of stormwater management infrastructure is estimated at $1.8 million. Any costs over $1.57 million are the responsibility of Gulf Breeze, FL.
Acres Acquired: 0
Close Year: 0
Close Month: 0
Close day: 0
Purchase Type: None
Landowner: None
Landowner Type: None
Purpose: None
Public Access: None
Easement Holder Name : None
Easement Holder Type: None
Secondary Easement Holder 1: None
Secondary Easement Holder 2: None
Duration: None
Term: 0
Land Restoration Acreage: 0
Aquatic Restoration Acreage: 0
Restoration Mileage: 0
Restoration Feet: 0
Additional Acreage:
Total Dollar Amount (from all funders): 1800000
DWH Funder: Florida Department of Environmental Protection
DWH Funder Type: State
DWH Funding Program: MOEX Clean Water Act Penalties (CWA)
DWH Dollar Amount : 1570000
DWH Source: MOEX
Fund Origin: Civil Settlement
Controlling Documents: Consent Decree Between The United States and MOEX Offshore 2007 LLC
Award Year: 2012
Award Month: 6
Total Amount Leveraged: 230000